Conclusion
The objective was a line size the developer could take into FEED with its conditions and its data needs stated. It was achieved. Every candidate diameter was tested on the same pressure and demand cases, the selected case was issued as conditional on the confirmed source pressure range, and the deliverable register was accepted as the basis for the FEED scope.
| Success criterion | Met | How it was achieved |
|---|
| iEvery candidate diameter tested against the same pressure and demand cases | Met | Hydraulic comparison issued for all cases with velocity and pressure drop tabulated |
| iiThe selected case stated with the condition that makes it valid | Met | Selected case issued as conditional on the confirmed source pressure range |
| iiiDrawings marked conceptual, not for construction | Met | Concept schemes issued at Revision C with the conceptual marking on every sheet |
| ivFEED data list issued with an owner and a check for each item | Met | Deliverable register accepted by the developer as the basis for the FEED scope |