Conclusion
The objective was a comment register the operator could act on and a sign-off recommendation before construction. Both were delivered. The traceability matrix covered every clause, the continuity gap between sheets was held and corrected, and the package went to construction with the hold cleared.
| Success criterion | Met | How it was achieved |
|---|
| iEvery clause of the statement of requirements traced to a drawing and tag or recorded as a gap | Met | Traceability matrix completed for all clauses |
| iiNo safety item open under a recommended-for-approval status | Met | Approval with conditions recommended; the continuity gap held and corrected on a revised sheet |
| iiiComments written so a third party can verify closure | Met | Comment register closed with the designer and the operator |
| ivHold items closed before issue for construction | Met | Package issued for construction with the hold cleared |