Conclusion
The objective was a new 16-inch line in service without a trip at the receiving facility, with the volumes it moved stated honestly. Both were achieved. The line reached first flow on the named well, the remaining wells moved across one at a time, the two temporary shut-ins were restored, and the moved volumes were reported from the allocation export rather than from the plan.
| Success criterion | Met | How it was achieved |
|---|
| iFirst flow achieved through the new line with no trip at the receiving facility | Met | First flow completed on the named well, and the remaining wells transferred one at a time with the facility stable between moves |
| iiEach hold point released on recorded evidence, with sign-off | Met | Hold point records and sign-offs filed with the commissioning dossier |
| iiiThe two temporary shut-ins returned to production after the transfer | Met | The shut-in wells restored once the receiving train had absorbed the transferred water |
| ivMoved volumes reported from the allocation export, not from the plan | Met | Planned figures of 8.8 and 13.1 thousand barrels a day kept as plan values; actuals taken from the allocation export after the event |